Project Requirement
With the lease term nearing its end Dabinett prepared a schedule of dilapidations and served this on the tenant.
Part of the claim was for the remediation of timber decay caused to the property by the tenant turning off a sump pump in the basement unit. Aside from repairs there was the necessity to decorate in accordance with the lease and to remove the tenants alterations.
The tenant undertook some works, but not the whole scope, many of the works that were carried out were to a poor standard. Where there had been former screens in place the tenant had removed these, but where there were cable holes were present wood patches has been installed.
Ultimately despite the tenant having spent some money, say £20,000, much of the work was still needed.
Negotiations started with the tenant’s surveyor and were met with an initial offer to settle at £10,000. With no meaningful progress and delaying tactics the works were tendered and then commenced.
Prior to works starting a Part 36 offer was made. There is further dicussion in the Tenant’s Guide to Leases series of articles. The crux was that an offer was made and the tenant didn’t accept, putting themselves is a difficult position, which in the end saw them settling at more than had been previously offered.
If a part 36 offer is made, not accepted by the other party, and matters progress to court then the sum of the final judgement can determine which party pays the costs post Part 36 offer. A party may successfully argue the merits of a case, but still have costs awarded against them. If the Part 36 is beaten then costs will be awarded against the other party (usually), ‘beaten’ is in the sense of the judgement being for a sum, more or less, than the Part 36. The basis being that had the offer been accepted all the costs associated with the litigation would have been avoided, therefore the party that declined the offer pays.